Project Milestones

PHASE I

Date Activity
October 2007 Commenced Field Investigations
January 2008 Commenced Preparatory Works
December 2008 River Diversion Completed

PHASE II

Date Activity
January - November 2009 Riverbed excavation & foundation works
December 2009 Commenced Main RCC Dam
June 2011 Commencement of Reservoir Filling
May 2013 Commissioned First Unit
July 2013 Commissioned Second Unit
December 2013 Completion and Commissioning of Bui Generating Station